Client Target Corporation

Western Distribution Center

Fontana, California

Target’s distribution center supports its retail store expansion on the West Coast. A phased, L-shaped design accommodated future expansion without disrupting operations.  Phase 1 included a 642,000-SF warehouse and 30,000-SF office. The site is near fault lines and a high wind corridor, so structural systems to seismic zone four specifications were implemented that allow infrastructure and AS/RS to move, while protecting merchandise during an earthquake. The building was also designed with sufficient lateral protection to support high winds. A series of exiting tunnels were incorporated into the design as a safety measure for employee egress. This facility was later expanded to a total of 1.4 million-SF.  LEO A DALY was also commissioned to design distribution centers in Arkansas, Colorado, and Minnesota.

At a glance

1.4 million SF

Features

Specialized Seismic Structural Design

Services

Architectural Design

Engineering:  Mechanical, Electrical, Structural